| 1-00589163 | 5 | LEST NPPDT | Line | 103rd & Rokeby - Moore NPPD 345 kV | 345 | 04/28/26 04:00:37 PM | Planned | COMPLETED | 06/02/26 08:00:00 AM | 06/02/26 04:00:00 PM | 06/02/26 08:46:00 AM | 06/02/26 04:15:00 PM |
| 1-00594600 | 6 | LEST OPPDT | Line | 103rd & Rokeby - S3458 345 kV | 345 | 05/21/26 08:07:43 AM | Planned | COMPLETED | 06/16/26 06:00:00 AM | 06/16/26 06:00:00 PM | 06/16/26 06:46:05 AM | 06/16/26 02:54:00 PM |
| 1-00589313 | 5 | LEST | Disconnect | 103rd & Rokeby 3061L | 345 | 04/29/26 02:06:47 PM | Planned | COMPLETED | 06/02/26 08:00:00 AM | 06/02/26 04:00:00 PM | 06/02/26 09:20:00 AM | 06/02/26 04:08:00 PM |
| 1-00594600 | 6 | LEST | Disconnect | 103rd & Rokeby 3066L | 345 | 05/21/26 08:07:43 AM | Planned | COMPLETED | 06/16/26 06:00:00 AM | 06/16/26 06:00:00 PM | 06/16/26 06:46:05 AM | 06/16/26 02:54:00 PM |
| 1-00574363 | 4 | AEPT | Line | 112_WGOR - AIRGSTMP 138 kV | 138 | 02/08/26 09:36:27 AM | Planned | SUBMITTED | 07/06/26 05:00:00 AM | 07/06/26 09:00:00 AM | | |
| 1-00605358 | 2 | AEPT | Line | 112_WGOR - AIRGSTMP 138 kV | 138 | 06/22/26 10:58:34 AM | Planned | APPROVED | 07/01/26 12:00:00 AM | 08/01/26 12:00:00 AM | | |
| 1-00484695 | 4 | AEPT | CircuitBreaker | 112_WGOR 2 P005N2 | 138 | 09/03/24 07:14:03 PM | Opportunity | IMPLEMENTED | 09/04/24 07:00:00 AM | 12/31/30 05:00:00 PM | 09/04/24 07:00:00 AM | |
| 1-00578582 | 5 | WRT | Line | 116th - Jarbalo 115 kV | 115 | 03/02/26 02:12:34 PM | Planned | COMPLETED | 05/26/26 07:00:00 AM | 06/05/26 03:00:00 PM | 05/26/26 10:34:00 AM | 05/29/26 01:03:00 PM |
| 1-00599536 | 3 | WRT | Disconnect | 12th & Clay 115-739 | 0 | 06/01/26 02:56:46 PM | Urgent | CANCELLED | 06/02/26 02:00:00 PM | 06/03/26 04:00:00 PM | | |
| 1-00599536 | 3 | WRT | Disconnect | 12th & Clay 115-743 | 0 | 06/01/26 02:56:46 PM | Urgent | CANCELLED | 06/02/26 02:00:00 PM | 06/03/26 04:00:00 PM | | |
| 1-00599536 | 3 | WRT | Disconnect | 12th & Clay 115-744 | 0 | 06/01/26 02:56:46 PM | Urgent | CANCELLED | 06/02/26 02:00:00 PM | 06/03/26 04:00:00 PM | | |
| 1-00599536 | 3 | WRT | Disconnect | 12th & Clay 115-749 | 0 | 06/01/26 02:56:46 PM | Urgent | CANCELLED | 06/02/26 02:00:00 PM | 06/03/26 04:00:00 PM | | |
| 1-00602510 | 6 | KCPLT MPST | Line | 13 & 40 - Mayview Tap 69 kV | 69 | 06/12/26 09:34:18 AM | Discretionary | COMPLETED | 06/22/26 08:00:00 AM | 06/22/26 12:00:00 PM | 06/22/26 08:30:00 AM | 06/22/26 12:50:00 PM |
| 1-00602397 | 1 | MPST | Line | 13 & 40 - Odessa 69kV | 69 | 06/11/26 02:37:15 PM | Planned | SUBMITTED | 08/10/26 08:00:00 AM | 08/28/26 04:00:00 PM | | |
| 1-00405250 | 8 | MPST | Line | 13 & 40 - Warrensburg Plant 69 kV | 69 | 03/14/23 02:38:56 PM | Planned | PREAPPROVED | 11/02/26 08:00:00 AM | 04/30/27 04:00:00 PM | | |
| 1-00602392 | 1 | MPST | Line | 13 & 40 - Warrensburg Plant 69 kV | 69 | 06/11/26 02:20:14 PM | Planned | SUBMITTED | 07/14/26 08:00:00 AM | 08/02/26 04:00:00 PM | | |
| 1-00602397 | 1 | MPST | CircuitBreaker | 13 & 40 R5 | 69 | 06/11/26 02:37:15 PM | Planned | SUBMITTED | 08/10/26 08:00:00 AM | 08/28/26 04:00:00 PM | | |
| 1-00405250 | 8 | MPST | CircuitBreaker | 13 & 40 R7 | 69 | 03/14/23 02:38:56 PM | Planned | PREAPPROVED | 11/02/26 08:00:00 AM | 04/30/27 04:00:00 PM | | |
| 1-00577437 | 8 | AEPT | Line | 136th Street & Yale - Riverside Station 138 kV | 138 | 02/22/26 06:47:54 PM | Planned | COMPLETED | 06/08/26 08:00:00 AM | 06/12/26 04:00:00 PM | 06/08/26 10:16:00 AM | 06/12/26 12:10:00 PM |
| 1-00577781 | 1 | AEPT | Line | 15th & Fulton - Tulsa Southeast 138 kV | 138 | 02/24/26 07:19:47 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 09/24/26 04:00:00 PM | | |
| 1-00577781 | 1 | AEPT | Disconnect | 15th & Fulton 1305B | 138 | 02/24/26 07:19:47 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 09/24/26 04:00:00 PM | | |
| 1-00577781 | 1 | AEPT | Line | 15th & Fulton Tap - Yale & Archer 138 kV | 138 | 02/24/26 07:19:47 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 09/24/26 04:00:00 PM | | |
| 1-00577781 | 1 | AEPT | Line | 15th & Fulton Tap - Zunis 138 kV | 138 | 02/24/26 07:19:47 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 09/24/26 04:00:00 PM | | |
| 1-00578582 | 5 | WRT | Disconnect | 166th 115-930 | 0 | 03/02/26 02:12:34 PM | Planned | COMPLETED | 05/26/26 07:00:00 AM | 06/05/26 03:00:00 PM | 05/26/26 10:34:00 AM | 05/29/26 01:03:00 PM |
| 1-00578582 | 5 | WRT | Disconnect | 166THSTR 4 115-932 | 115 | 03/02/26 02:12:34 PM | Planned | COMPLETED | 05/26/26 07:00:00 AM | 06/05/26 03:00:00 PM | 05/26/26 10:34:00 AM | 05/29/26 01:03:00 PM |
| 1-00600219 | 2 | WRT | Line | 17th & Fairlawn - Indian Hills 115 kV | 115 | 06/04/26 10:44:51 PM | Forced | COMPLETED | 06/04/26 10:44:00 PM | 06/08/26 04:00:00 PM | 06/04/26 10:44:00 PM | 06/05/26 11:32:00 AM |
| 1-00600219 | 2 | WRT | CircuitBreaker | 17th & Fairlawn 115-1364 | 115 | 06/04/26 10:44:51 PM | Forced | COMPLETED | 06/04/26 10:44:00 PM | 06/08/26 04:00:00 PM | 06/04/26 10:44:00 PM | 06/05/26 11:32:00 AM |
| 1-00590424 | 7 | WRT | CircuitBreaker | 17th & Fairlawn 115-518 | 115 | 05/07/26 10:06:49 AM | Planned | COMPLETED | 06/08/26 06:00:00 AM | 06/26/26 04:00:00 PM | 06/08/26 06:31:00 AM | 06/24/26 04:14:00 PM |
| 1-00590990 | 2 | LEST | Line | 17th & Holdrege - 21st & N 115 kV | 115 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00603928 | 1 | LEST | Line | 17th & Holdrege - 8th & N 115 kV | 115 | 06/19/26 10:06:57 AM | Planned | SUBMITTED | 07/07/26 08:00:00 AM | 07/07/26 04:00:00 PM | | |
| 1-00590990 | 2 | LEST | Disconnect | 17th & Holdrege 1062 | 115 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00603928 | 1 | LEST | Disconnect | 17th & Holdrege 1063 | 115 | 06/19/26 10:06:57 AM | Planned | SUBMITTED | 07/07/26 08:00:00 AM | 07/07/26 04:00:00 PM | | |
| 1-00600188 | 4 | LEST | CircuitBreaker | 19th & Alvo 1001 | 115 | 06/04/26 03:20:17 PM | Planned | IMPLEMENTED | 06/22/26 08:00:00 AM | 06/25/26 04:00:00 PM | 06/22/26 09:31:00 AM | |
| 1-00600188 | 4 | LEST | Disconnect | 19th & Alvo 1001_D1 | 115 | 06/04/26 03:20:17 PM | Planned | IMPLEMENTED | 06/22/26 08:00:00 AM | 06/25/26 04:00:00 PM | 06/22/26 09:31:00 AM | |
| 1-00600188 | 4 | LEST | Disconnect | 19th & Alvo 1001_D2 | 115 | 06/04/26 03:20:17 PM | Planned | IMPLEMENTED | 06/22/26 08:00:00 AM | 06/25/26 04:00:00 PM | 06/22/26 09:31:00 AM | |
| 1-00599386 | 5 | LEST | CircuitBreaker | 19th & Alvo 1003 | 115 | 06/01/26 07:44:11 AM | Planned | COMPLETED | 06/15/26 08:00:00 AM | 06/16/26 04:00:00 PM | 06/15/26 01:58:00 PM | 06/16/26 03:10:00 PM |
| 1-00599386 | 5 | LEST | Disconnect | 19th & Alvo 1003_D1 | 115 | 06/01/26 07:44:11 AM | Planned | COMPLETED | 06/15/26 08:00:00 AM | 06/16/26 04:00:00 PM | 06/15/26 01:58:00 PM | 06/16/26 03:10:00 PM |
| 1-00599386 | 5 | LEST | Disconnect | 19th & Alvo 1003_D2 | 115 | 06/01/26 07:44:11 AM | Planned | COMPLETED | 06/15/26 08:00:00 AM | 06/16/26 04:00:00 PM | 06/15/26 01:58:00 PM | 06/16/26 03:10:00 PM |
| 1-00599392 | 5 | LEST | CircuitBreaker | 19th & Alvo 1004 | 115 | 06/01/26 07:53:51 AM | Planned | COMPLETED | 06/17/26 08:00:00 AM | 06/18/26 04:00:00 PM | 06/17/26 08:48:00 AM | 06/18/26 12:25:00 PM |
| 1-00599392 | 5 | LEST | Disconnect | 19th & Alvo 1004_D1 | 115 | 06/01/26 07:53:51 AM | Planned | COMPLETED | 06/17/26 08:00:00 AM | 06/18/26 04:00:00 PM | 06/17/26 08:48:00 AM | 06/18/26 12:25:00 PM |
| 1-00599392 | 5 | LEST | Disconnect | 19th & Alvo 1004_D2 | 115 | 06/01/26 07:53:51 AM | Planned | COMPLETED | 06/17/26 08:00:00 AM | 06/18/26 04:00:00 PM | 06/17/26 08:48:00 AM | 06/18/26 12:25:00 PM |
| 1-00551819 | 8 | LEST | Line | 20th & Pioneer - 40th & Gertie 115 kV | 115 | 10/06/25 02:42:08 PM | Planned | IMPLEMENTED | 01/12/26 09:00:00 AM | 06/25/26 04:00:00 PM | 01/12/26 12:54:00 PM | |
| 1-00551819 | 8 | LEST | CircuitBreaker | 20th & Pioneer 1061_L | 115 | 10/06/25 02:42:08 PM | Planned | IMPLEMENTED | 01/12/26 09:00:00 AM | 06/25/26 04:00:00 PM | 01/12/26 12:54:00 PM | |
| 1-00596564 | 1 | LEST | Line | 21st & N - 30th & A 115 kV | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00590991 | 2 | LEST | Line | 21st & N - 30th & A 115 kV | 115 | 05/11/26 02:06:08 PM | Planned | SUBMITTED | 07/20/26 08:00:00 AM | 07/24/26 04:00:00 PM | | |
| 1-00590991 | 2 | LEST | CircuitBreaker | 21st & N 1001 | 115 | 05/11/26 02:06:08 PM | Planned | SUBMITTED | 07/20/26 08:00:00 AM | 07/24/26 04:00:00 PM | | |
| 1-00590990 | 2 | LEST | CircuitBreaker | 21st & N 1001 | 115 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00590991 | 2 | LEST | Disconnect | 21st & N 1001-D1 | 0 | 05/11/26 02:06:08 PM | Planned | SUBMITTED | 07/20/26 08:00:00 AM | 07/24/26 04:00:00 PM | | |
| 1-00590990 | 2 | LEST | Disconnect | 21st & N 1001-D1 | 0 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00590991 | 2 | LEST | Disconnect | 21st & N 1001-D2 | 0 | 05/11/26 02:06:08 PM | Planned | SUBMITTED | 07/20/26 08:00:00 AM | 07/24/26 04:00:00 PM | | |
| 1-00590990 | 2 | LEST | Disconnect | 21st & N 1001-D2 | 0 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00590990 | 2 | LEST | Disconnect | 21st & N 1061L | 0 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | Disconnect | 21st & N 1062L | 0 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00590991 | 2 | LEST | Disconnect | 21st & N 1062L | 0 | 05/11/26 02:06:08 PM | Planned | SUBMITTED | 07/20/26 08:00:00 AM | 07/24/26 04:00:00 PM | | |
| 1-00590990 | 2 | LEST | CircuitBreaker | 21st & N 4810 | 115 | 05/11/26 02:04:37 PM | Planned | SUBMITTED | 07/13/26 08:00:00 AM | 07/17/26 04:00:00 PM | | |
| 1-00578584 | 8 | WRT | Line | 27th & Croco - 41st & California 115 kV #1 | 115 | 03/02/26 02:17:05 PM | Planned | COMPLETED | 06/09/26 06:00:00 AM | 06/19/26 07:00:00 PM | 06/09/26 06:47:00 AM | 06/19/26 11:13:00 AM |
| 1-00578584 | 8 | WRT | Disconnect | 27th & Croco 115-402 | 0 | 03/02/26 02:17:05 PM | Planned | COMPLETED | 06/09/26 06:00:00 AM | 06/19/26 07:00:00 PM | 06/09/26 06:47:00 AM | 06/19/26 11:13:00 AM |
| 1-00590136 | 10 | LEST | Line | 27th & Pine Lake - 40th & Rokeby 115 kV | 115 | 05/05/26 02:25:29 PM | Discretionary | COMPLETED | 05/11/26 08:00:00 AM | 06/01/26 04:00:00 PM | 05/11/26 08:30:00 AM | 06/01/26 09:15:00 AM |
| 1-00590136 | 10 | LEST | CircuitBreaker | 27th & Pine Lake 1062-L | 115 | 05/05/26 02:25:29 PM | Discretionary | COMPLETED | 05/11/26 08:00:00 AM | 06/01/26 04:00:00 PM | 05/11/26 08:30:00 AM | 06/01/26 09:15:00 AM |
| 1-00590424 | 7 | WRT | Line | 29th & Eveningside Jct - 17th & Fairlawn 115kV | 115 | 05/07/26 10:06:49 AM | Planned | COMPLETED | 06/08/26 06:00:00 AM | 06/26/26 04:00:00 PM | 06/08/26 06:31:00 AM | 06/24/26 04:14:00 PM |
| 1-00590424 | 7 | WRT | Line | 29th & Eveningside Jct - 29th & Gage 115kV | 115 | 05/07/26 10:06:49 AM | Planned | COMPLETED | 06/08/26 06:00:00 AM | 06/26/26 04:00:00 PM | 06/08/26 06:31:00 AM | 06/24/26 04:14:00 PM |
| 1-00606791 | 1 | WRT | Line | 29th & Gage - Quinton Heights 115 kV | 115 | 06/24/26 01:26:40 PM | Planned | SUBMITTED | 07/13/26 06:00:00 AM | 07/16/26 04:00:00 PM | | |
| 1-00590424 | 7 | WRT | Disconnect | 29th & Gage 115-339 | 0 | 05/07/26 10:06:49 AM | Planned | COMPLETED | 06/08/26 06:00:00 AM | 06/26/26 04:00:00 PM | 06/08/26 06:31:00 AM | 06/24/26 04:14:00 PM |
| 1-00606791 | 1 | WRT | Disconnect | 29th & Gage 115-343 | 0 | 06/24/26 01:26:40 PM | Planned | SUBMITTED | 07/13/26 06:00:00 AM | 07/16/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | Line | 2nd & N - 8th & N 115 kV | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | CircuitBreaker | 2nd & N 1001 | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | Disconnect | 2nd & N 1001_D1 | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | Disconnect | 2nd & N 1001_D2 | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | CircuitBreaker | 2nd & N 1002 | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | Disconnect | 2nd & N 1002_D1 | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | Disconnect | 2nd & N 1002_D2 | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00603855 | 1 | LEST | CircuitBreaker | 2nd & N 1061L | 115 | 06/18/26 07:52:20 PM | Planned | SUBMITTED | 08/31/26 08:00:00 AM | 09/04/26 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | Line | 30th & A - 56th & Everett 115 kV | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | CircuitBreaker | 30th & A 1001 | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | Disconnect | 30th & A 1001_D1 | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | Disconnect | 30th & A 1001_D2 | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | Disconnect | 30th & A 1061L | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00590991 | 2 | LEST | Disconnect | 30th & A 1061L | 115 | 05/11/26 02:06:08 PM | Planned | SUBMITTED | 07/20/26 08:00:00 AM | 07/24/26 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | Disconnect | 30th & A 1062L | 0 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | CircuitBreaker | 30th & A 5210 | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00596564 | 1 | LEST | CircuitBreaker | 30th & A 5220 | 115 | 05/27/26 02:09:25 PM | Planned | SUBMITTED | 09/14/26 08:00:00 AM | 05/28/27 04:00:00 PM | | |
| 1-00595314 | 1 | LEST | Line | 33rd & Superior - 59th & Cornhusker 115 kV | 115 | 05/26/26 11:37:49 AM | Planned | SUBMITTED | 08/10/26 08:00:00 AM | 08/21/26 04:00:00 PM | | |
| 1-00595314 | 1 | LEST | CircuitBreaker | 33rd & Superior 3359_L | 115 | 05/26/26 11:37:49 AM | Planned | SUBMITTED | 08/10/26 08:00:00 AM | 08/21/26 04:00:00 PM | | |
| 1-00597763 | 2 | OKGET | Line | 36 & Meridian - Hobby Lobby 138 kV | 138 | 05/28/26 01:21:56 PM | Planned | SUBMITTED | 06/29/26 09:00:00 AM | 07/09/26 05:00:00 PM | | |
| 1-00597763 | 2 | OKGET | Line | 36 & Meridian - SW 5th 138 kV | 138 | 05/28/26 01:21:56 PM | Planned | SUBMITTED | 06/29/26 09:00:00 AM | 07/09/26 05:00:00 PM | | |
| 1-00597763 | 2 | OKGET | Line | 36 & Meridian - Will Rogers Airport 138 kV | 138 | 05/28/26 01:21:56 PM | Planned | SUBMITTED | 06/29/26 09:00:00 AM | 07/09/26 05:00:00 PM | | |
| 1-00599955 | 1 | OKGET | Line | 38th Street - May Ave 69 kV | 69 | 06/03/26 12:04:53 PM | Planned | SUBMITTED | 06/29/26 09:00:00 AM | 06/30/26 04:30:00 PM | | |
| 1-00595389 | 4 | OKGET | Line | 3rd Street - Arkoma 161 kV | 161 | 05/26/26 03:29:24 PM | Planned | SUBMITTED | 07/06/26 08:30:00 AM | 07/07/26 03:00:00 PM | | |
| 1-00596480 | 4 | OKGET | Line | 3rd Street - J Street 161 kV | 161 | 05/27/26 08:57:15 AM | Planned | SUBMITTED | 07/08/26 08:00:00 AM | 07/09/26 03:00:00 PM | | |
| 1-00596484 | 4 | OKGET | Line | 3rd Street - Muldrow Tap 69 kV | 69 | 05/27/26 09:30:32 AM | Planned | COMPLETED | 06/15/26 08:30:00 AM | 06/16/26 02:00:00 PM | 06/15/26 09:34:29 AM | 06/16/26 01:32:49 PM |
| 1-00595389 | 4 | OKGET | Disconnect | 3rd Street 124 | 0 | 05/26/26 03:29:24 PM | Planned | SUBMITTED | 07/06/26 08:30:00 AM | 07/07/26 03:00:00 PM | | |
| 1-00599005 | 2 | OKGET | Disconnect | 3rd Street 124 | 0 | 05/29/26 09:16:49 PM | Forced | COMPLETED | 05/29/26 09:16:00 PM | 06/01/26 05:00:00 PM | 05/29/26 09:16:22 PM | 06/01/26 11:09:55 AM |
| 1-00596480 | 4 | OKGET | Disconnect | 3rd Street 131 | 161 | 05/27/26 08:57:15 AM | Planned | SUBMITTED | 07/08/26 08:00:00 AM | 07/09/26 03:00:00 PM | | |
| 1-00595389 | 4 | OKGET | Disconnect | 3rd Street 132 | 161 | 05/26/26 03:29:24 PM | Planned | SUBMITTED | 07/06/26 08:30:00 AM | 07/07/26 03:00:00 PM | | |
| 1-00595389 | 4 | OKGET | Transformer | 3rd Street 161/69 kV XFMR #4 | 69 | 05/26/26 03:29:24 PM | Planned | SUBMITTED | 07/06/26 08:30:00 AM | 07/07/26 03:00:00 PM | | |
| 1-00596480 | 4 | OKGET | Transformer | 3rd Street 161/69 kV XFMR #5 | 69 | 05/27/26 08:57:15 AM | Planned | SUBMITTED | 07/08/26 08:00:00 AM | 07/09/26 03:00:00 PM | | |
| 1-00596488 | 5 | OKGET | CircuitBreaker | 3rd Street Circuit Breaker 82 | 69 | 05/27/26 09:45:25 AM | Planned | COMPLETED | 06/18/26 08:00:00 AM | 06/18/26 02:00:00 PM | 06/18/26 08:22:39 AM | 06/18/26 11:13:30 AM |
| 1-00596531 | 4 | OKGET | CircuitBreaker | 3rd Street Circuit Breaker 83 | 69 | 05/27/26 12:12:55 PM | Planned | COMPLETED | 06/18/26 08:30:00 AM | 06/18/26 02:00:00 PM | 06/18/26 12:43:00 PM | 06/18/26 01:44:44 PM |
| 1-00596484 | 4 | OKGET | CircuitBreaker | 3rd Street Circuit Breaker 84 | 69 | 05/27/26 09:30:32 AM | Planned | COMPLETED | 06/15/26 08:30:00 AM | 06/16/26 02:00:00 PM | 06/15/26 09:34:29 AM | 06/16/26 01:32:49 PM |
| 1-00596484 | 4 | OKGET | CircuitBreaker | 3rd Street Circuit Breaker 86 | 69 | 05/27/26 09:30:32 AM | Planned | COMPLETED | 06/15/26 08:30:00 AM | 06/16/26 02:00:00 PM | 06/15/26 09:34:29 AM | 06/16/26 01:32:49 PM |