1-00484695 | 4 | AEPT | CircuitBreaker | 112_WGOR 2 P005N2 | 138 | 09/03/24 07:14:03 PM | Opportunity | IMPLEMENTED | 09/04/24 07:00:00 AM | 12/31/30 05:00:00 PM | 09/04/24 07:00:00 AM | |
1-00536568 | 8 | AEPT | Disconnect | 116PEORI 4 P00268 | 138 | 06/25/25 01:53:10 PM | Planned | PREAPPROVED | 09/29/25 08:00:00 AM | 10/03/25 04:00:00 PM | | |
1-00535720 | 2 | AEPT | Disconnect | 116PEORI 4 P00277 | 138 | 06/19/25 10:14:04 AM | Planned | PREAPPROVED | 09/15/25 08:00:00 AM | 09/15/25 04:00:00 PM | | |
1-00541840 | 2 | AEPT | Disconnect | 116PEORI 4 P00277 | 138 | 07/29/25 08:36:16 AM | Planned | PREAPPROVED | 10/06/25 08:00:00 AM | 10/10/25 04:00:00 PM | | |
1-00535720 | 2 | AEPT | Line | 116th Street & Peoria - Jenks 138 kV | 138 | 06/19/25 10:14:04 AM | Planned | PREAPPROVED | 09/15/25 08:00:00 AM | 09/15/25 04:00:00 PM | | |
1-00541840 | 2 | AEPT | Line | 116th Street & Peoria - Jenks 138 kV | 138 | 07/29/25 08:36:16 AM | Planned | PREAPPROVED | 10/06/25 08:00:00 AM | 10/10/25 04:00:00 PM | | |
1-00536568 | 8 | AEPT | Line | 116th Street & Peoria - Riverside Station 138 kV | 138 | 06/25/25 01:53:10 PM | Planned | PREAPPROVED | 09/29/25 08:00:00 AM | 10/03/25 04:00:00 PM | | |
1-00533492 | 4 | MPST | Line | 13 & 40 - Odessa 69kV | 69 | 06/03/25 01:24:56 PM | Planned | IMPLEMENTED | 08/25/25 08:00:00 AM | 09/12/25 05:00:00 PM | 08/25/25 08:14:00 AM | |
1-00521982 | 8 | MPST | Line | 13 & 40 - Odessa 69kV | 69 | 03/26/25 10:31:51 AM | Planned | COMPLETED | 07/07/25 07:00:00 AM | 08/08/25 05:00:00 PM | 07/07/25 07:44:00 AM | 08/08/25 12:06:00 PM |
1-00405250 | 5 | MPST | Line | 13 & 40 - Warrensburg Plant 69 kV | 69 | 03/14/23 02:38:56 PM | Planned | PREAPPROVED | 11/03/25 08:00:00 AM | 04/30/26 04:00:00 PM | | |
1-00533492 | 4 | MPST | CircuitBreaker | 13 & 40 R5 | 69 | 06/03/25 01:24:56 PM | Planned | IMPLEMENTED | 08/25/25 08:00:00 AM | 09/12/25 05:00:00 PM | 08/25/25 08:14:00 AM | |
1-00521982 | 8 | MPST | CircuitBreaker | 13 & 40 R5 | 69 | 03/26/25 10:31:51 AM | Planned | COMPLETED | 07/07/25 07:00:00 AM | 08/08/25 05:00:00 PM | 07/07/25 07:44:00 AM | 08/08/25 12:06:00 PM |
1-00405250 | 5 | MPST | CircuitBreaker | 13 & 40 R7 | 69 | 03/14/23 02:38:56 PM | Planned | PREAPPROVED | 11/03/25 08:00:00 AM | 04/30/26 04:00:00 PM | | |
1-00526241 | 10 | AEPT | Line | 15th & Fulton - Tulsa Southeast 138 kV | 138 | 04/30/25 08:05:23 AM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00526241 | 10 | AEPT | Disconnect | 15th & Fulton 1305B | 138 | 04/30/25 08:05:23 AM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00526241 | 10 | AEPT | Line | 15th & Fulton Tap - Yale & Archer 138 kV | 138 | 04/30/25 08:05:23 AM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00526241 | 10 | AEPT | Line | 15th & Fulton Tap - Zunis 138 kV | 138 | 04/30/25 08:05:23 AM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00540023 | 3 | WRT | Line | 17th & Fairlawn - Indian Hills 115 kV | 115 | 07/14/25 01:56:16 PM | Planned | APPROVED | 09/04/25 11:00:00 AM | 09/08/25 02:00:00 PM | | |
1-00540023 | 3 | WRT | CircuitBreaker | 17th & Fairlawn 115-1364 | 115 | 07/14/25 01:56:16 PM | Planned | APPROVED | 09/04/25 11:00:00 AM | 09/08/25 02:00:00 PM | | |
1-00545761 | 2 | WRT | CircuitBreaker | 17th 69-14 | 69 | 08/26/25 12:22:10 PM | Planned | PREAPPROVED | 09/11/25 09:01:00 AM | 10/31/25 04:00:00 PM | | |
1-00540047 | 6 | WRT | CircuitBreaker | 17th 69-14 | 69 | 07/14/25 03:47:27 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/04/25 12:59:00 PM | 08/04/25 07:04:00 AM | 08/04/25 11:59:00 AM |
1-00545761 | 2 | WRT | Line | 17th Tap - 17th | 69 | 08/26/25 12:22:10 PM | Planned | PREAPPROVED | 09/11/25 09:01:00 AM | 10/31/25 04:00:00 PM | | |
1-00540047 | 6 | WRT | Line | 17th Tap - 17th | 69 | 07/14/25 03:47:27 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/04/25 12:59:00 PM | 08/04/25 07:04:00 AM | 08/04/25 11:59:00 AM |
1-00540034 | 5 | WRT | Line | 17th Tap - Riverside 69kV | 69 | 07/14/25 02:39:29 PM | Planned | IMPLEMENTED | 08/04/25 01:00:00 PM | 09/11/25 09:00:00 AM | 08/04/25 11:39:00 AM | |
1-00545761 | 2 | WRT | Line | 17th Tap - Riverside 69kV | 69 | 08/26/25 12:22:10 PM | Planned | PREAPPROVED | 09/11/25 09:01:00 AM | 10/31/25 04:00:00 PM | | |
1-00540047 | 6 | WRT | Line | 17th Tap - Riverside 69kV | 69 | 07/14/25 03:47:27 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/04/25 12:59:00 PM | 08/04/25 07:04:00 AM | 08/04/25 11:59:00 AM |
1-00545761 | 2 | WRT | Line | 17th Tap - Webster 69kV | 69 | 08/26/25 12:22:10 PM | Planned | PREAPPROVED | 09/11/25 09:01:00 AM | 10/31/25 04:00:00 PM | | |
1-00540047 | 6 | WRT | Line | 17th Tap - Webster 69kV | 69 | 07/14/25 03:47:27 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/04/25 12:59:00 PM | 08/04/25 07:04:00 AM | 08/04/25 11:59:00 AM |
1-00539985 | 7 | WRT | Disconnect | 18th & Plum 69-61 | 0 | 07/14/25 11:07:39 AM | Planned | COMPLETED | 08/05/25 08:00:00 AM | 08/07/25 04:00:00 PM | 08/05/25 08:09:00 AM | 08/07/25 03:42:00 PM |
1-00510924 | 6 | LEST | Line | 19th & Alvo - 56th & I 80 115 kV | 115 | 01/20/25 02:33:28 PM | Planned | IMPLEMENTED | 07/14/25 08:00:00 AM | 10/20/25 04:00:00 PM | 07/14/25 07:59:00 AM | |
1-00543241 | 5 | LEST | CircuitBreaker | 19th & Alvo 1002 | 115 | 08/07/25 02:09:12 PM | Discretionary | COMPLETED | 08/11/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/11/25 08:39:00 AM | 08/14/25 08:11:00 AM |
1-00543241 | 5 | LEST | Disconnect | 19th & Alvo 1002_D1 | 115 | 08/07/25 02:09:12 PM | Discretionary | COMPLETED | 08/11/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/11/25 08:39:00 AM | 08/14/25 08:11:00 AM |
1-00543241 | 5 | LEST | Disconnect | 19th & Alvo 1002_D2 | 115 | 08/07/25 02:09:12 PM | Discretionary | COMPLETED | 08/11/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/11/25 08:39:00 AM | 08/14/25 08:11:00 AM |
1-00543241 | 5 | LEST | CircuitBreaker | 19th & Alvo 1003 | 115 | 08/07/25 02:09:12 PM | Discretionary | COMPLETED | 08/11/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/11/25 08:39:00 AM | 08/14/25 08:11:00 AM |
1-00543241 | 5 | LEST | Disconnect | 19th & Alvo 1003_D1 | 115 | 08/07/25 02:09:12 PM | Discretionary | COMPLETED | 08/11/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/11/25 08:39:00 AM | 08/14/25 08:11:00 AM |
1-00543241 | 5 | LEST | Disconnect | 19th & Alvo 1003_D2 | 115 | 08/07/25 02:09:12 PM | Discretionary | COMPLETED | 08/11/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/11/25 08:39:00 AM | 08/14/25 08:11:00 AM |
1-00510924 | 6 | LEST | CircuitBreaker | 19th & Alvo 1062L | 115 | 01/20/25 02:33:28 PM | Planned | IMPLEMENTED | 07/14/25 08:00:00 AM | 10/20/25 04:00:00 PM | 07/14/25 07:59:00 AM | |
1-00535454 | 3 | WRT | Line | 29th & Eveningside Jct - 29th & Gage 115kV | 115 | 06/17/25 03:16:17 PM | Planned | PREAPPROVED | 09/08/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00541619 | 4 | WRT | Line | 29th & Gage - Quinton Heights 115 kV | 115 | 07/27/25 03:33:34 PM | Forced | COMPLETED | 07/27/25 03:30:00 PM | 08/06/25 04:00:00 PM | 07/27/25 03:30:00 PM | 08/04/25 10:27:00 AM |
1-00535454 | 3 | WRT | Disconnect | 29th & Gage 115-339 | 0 | 06/17/25 03:16:17 PM | Planned | PREAPPROVED | 09/08/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00535454 | 3 | WRT | Disconnect | 29th & Gage 115-340 | 0 | 06/17/25 03:16:17 PM | Planned | PREAPPROVED | 09/08/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00535454 | 3 | WRT | Disconnect | 29th & Gage 115-341 | 0 | 06/17/25 03:16:17 PM | Planned | PREAPPROVED | 09/08/25 08:00:00 AM | 09/19/25 05:00:00 PM | | |
1-00536495 | 2 | WRT | Disconnect | 2MAD 4 2514 | 115 | 06/25/25 08:46:37 AM | Planned | PREAPPROVED | 10/13/25 08:00:00 AM | 11/07/25 04:00:00 PM | | |
1-00539985 | 7 | WRT | Line | 2nd & Elm - Maple Street Junction 69 kV | 69 | 07/14/25 11:07:39 AM | Planned | COMPLETED | 08/05/25 08:00:00 AM | 08/07/25 04:00:00 PM | 08/05/25 08:09:00 AM | 08/07/25 03:42:00 PM |
1-00536495 | 2 | WRT | Line | 2nd & Madison - 4th & Van Buren 115 kV | 115 | 06/25/25 08:46:37 AM | Planned | PREAPPROVED | 10/13/25 08:00:00 AM | 11/07/25 04:00:00 PM | | |
1-00536712 | 5 | LEST | CircuitBreaker | 2nd & N 1001 | 115 | 06/26/25 12:04:48 PM | Planned | COMPLETED | 08/18/25 08:00:00 AM | 08/19/25 04:00:00 PM | 08/18/25 09:09:00 AM | 08/19/25 03:07:00 PM |
1-00536712 | 5 | LEST | Disconnect | 2nd & N 1001_D1 | 115 | 06/26/25 12:04:48 PM | Planned | COMPLETED | 08/18/25 08:00:00 AM | 08/19/25 04:00:00 PM | 08/18/25 09:09:00 AM | 08/19/25 03:07:00 PM |
1-00536712 | 5 | LEST | Disconnect | 2nd & N 1001_D2 | 115 | 06/26/25 12:04:48 PM | Planned | COMPLETED | 08/18/25 08:00:00 AM | 08/19/25 04:00:00 PM | 08/18/25 09:09:00 AM | 08/19/25 03:07:00 PM |
1-00536713 | 5 | LEST | CircuitBreaker | 2nd & N 1002 | 115 | 06/26/25 12:06:53 PM | Planned | COMPLETED | 08/20/25 08:00:00 AM | 08/21/25 04:00:00 PM | 08/20/25 08:27:00 AM | 08/21/25 03:17:00 PM |
1-00536713 | 5 | LEST | Disconnect | 2nd & N 1002_D1 | 115 | 06/26/25 12:06:53 PM | Planned | COMPLETED | 08/20/25 08:00:00 AM | 08/21/25 04:00:00 PM | 08/20/25 08:27:00 AM | 08/21/25 03:17:00 PM |
1-00536713 | 5 | LEST | Disconnect | 2nd & N 1002_D2 | 115 | 06/26/25 12:06:53 PM | Planned | COMPLETED | 08/20/25 08:00:00 AM | 08/21/25 04:00:00 PM | 08/20/25 08:27:00 AM | 08/21/25 03:17:00 PM |
1-00536714 | 5 | LEST | CircuitBreaker | 2nd & N 1003 | 115 | 06/26/25 12:08:44 PM | Planned | COMPLETED | 08/25/25 08:00:00 AM | 08/26/25 04:00:00 PM | 08/25/25 08:32:00 AM | 08/26/25 01:43:00 PM |
1-00536714 | 5 | LEST | Disconnect | 2nd & N 1003_D1 | 115 | 06/26/25 12:08:44 PM | Planned | COMPLETED | 08/25/25 08:00:00 AM | 08/26/25 04:00:00 PM | 08/25/25 08:32:00 AM | 08/26/25 01:43:00 PM |
1-00536714 | 5 | LEST | Disconnect | 2nd & N 1003_D2 | 115 | 06/26/25 12:08:44 PM | Planned | COMPLETED | 08/25/25 08:00:00 AM | 08/26/25 04:00:00 PM | 08/25/25 08:32:00 AM | 08/26/25 01:43:00 PM |
1-00536719 | 5 | LEST | CircuitBreaker | 2nd & N 1004 | 115 | 06/26/25 12:50:36 PM | Planned | COMPLETED | 08/27/25 08:00:00 AM | 08/28/25 04:00:00 PM | 08/27/25 08:38:00 AM | 08/28/25 12:50:00 PM |
1-00536719 | 5 | LEST | Disconnect | 2nd & N 1004_D1 | 115 | 06/26/25 12:50:36 PM | Planned | COMPLETED | 08/27/25 08:00:00 AM | 08/28/25 04:00:00 PM | 08/27/25 08:38:00 AM | 08/28/25 12:50:00 PM |
1-00536719 | 5 | LEST | Disconnect | 2nd & N 1004_D2 | 115 | 06/26/25 12:50:36 PM | Planned | COMPLETED | 08/27/25 08:00:00 AM | 08/28/25 04:00:00 PM | 08/27/25 08:38:00 AM | 08/28/25 12:50:00 PM |
1-00536721 | 4 | LEST | CircuitBreaker | 2nd & N 1005 | 115 | 06/26/25 12:52:30 PM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/03/25 04:00:00 PM | | |
1-00536721 | 4 | LEST | Disconnect | 2nd & N 1005_D1 | 115 | 06/26/25 12:52:30 PM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/03/25 04:00:00 PM | | |
1-00536721 | 4 | LEST | Disconnect | 2nd & N 1005_D2 | 115 | 06/26/25 12:52:30 PM | Planned | APPROVED | 09/02/25 08:00:00 AM | 09/03/25 04:00:00 PM | | |
1-00545839 | 4 | LEST | Disconnect | 2nd & N 3092 | 115 | 08/26/25 07:08:36 PM | Urgent | COMPLETED | 08/28/25 08:00:00 AM | 08/28/25 04:00:00 PM | 08/28/25 12:50:00 PM | 08/28/25 02:42:00 PM |
1-00545839 | 4 | LEST | Disconnect | 2nd & N 3092D | 0 | 08/26/25 07:08:36 PM | Urgent | COMPLETED | 08/28/25 08:00:00 AM | 08/28/25 04:00:00 PM | 08/28/25 12:50:00 PM | 08/28/25 02:42:00 PM |
1-00535376 | 2 | AEPT | Line | 36th Street & Lewis - Tulsa Power Station 138 kV | 138 | 06/17/25 09:56:12 AM | Planned | PREAPPROVED | 11/24/25 08:00:00 AM | 12/18/25 05:00:00 PM | | |
1-00535724 | 2 | AEPT | Disconnect | 36th Street & Lewis 1398M | 138 | 06/19/25 10:54:55 AM | Planned | PREAPPROVED | 09/15/25 08:00:00 AM | 09/18/25 05:00:00 PM | | |
1-00537164 | 2 | AEPT | Disconnect | 36th Street & Lewis 1398M | 138 | 06/30/25 01:46:52 PM | Planned | PREAPPROVED | 09/22/25 08:00:00 AM | 11/20/25 05:00:00 PM | | |
1-00535376 | 2 | AEPT | CircuitBreaker | 36th Street & Lewis CB 1301A | 138 | 06/17/25 09:56:12 AM | Planned | PREAPPROVED | 11/24/25 08:00:00 AM | 12/18/25 05:00:00 PM | | |
1-00537164 | 2 | AEPT | CircuitBreaker | 36th Street & Lewis CB 1301A | 138 | 06/30/25 01:46:52 PM | Planned | PREAPPROVED | 09/22/25 08:00:00 AM | 11/20/25 05:00:00 PM | | |
1-00538124 | 6 | WRT | Line | 3rd & Van Buren - East & Madison Junction 69 kV | 69 | 07/08/25 01:26:33 PM | Discretionary | COMPLETED | 07/21/25 06:00:00 AM | 08/01/25 04:00:00 PM | 07/21/25 09:38:00 AM | 08/01/25 05:56:00 AM |
1-00541088 | 5 | WRT | Line | 3rd & Van Buren - Meadowlark 115 kV #1 | 115 | 07/22/25 02:35:36 PM | Operational | COMPLETED | 07/22/25 04:00:00 PM | 10/01/25 04:00:00 PM | 07/22/25 03:02:00 PM | 08/06/25 04:46:00 PM |
1-00538124 | 6 | WRT | Transformer | 3rd & Van Buren 115/69 kV XFMR | 69 | 07/08/25 01:26:33 PM | Discretionary | COMPLETED | 07/21/25 06:00:00 AM | 08/01/25 04:00:00 PM | 07/21/25 09:38:00 AM | 08/01/25 05:56:00 AM |
1-00538124 | 6 | WRT | CircuitBreaker | 3rd & Van Buren 115-661 | 115 | 07/08/25 01:26:33 PM | Discretionary | COMPLETED | 07/21/25 06:00:00 AM | 08/01/25 04:00:00 PM | 07/21/25 09:38:00 AM | 08/01/25 05:56:00 AM |
1-00543068 | 3 | WRT | CircuitBreaker | 3rd & Van Buren 115-999 | 115 | 08/06/25 04:42:24 PM | Operational | IMPLEMENTED | 08/06/25 05:00:00 PM | 10/01/25 04:00:00 PM | 08/06/25 04:46:00 PM | |
1-00538124 | 6 | WRT | CircuitBreaker | 3rd & Van Buren 69-66 | 69 | 07/08/25 01:26:33 PM | Discretionary | COMPLETED | 07/21/25 06:00:00 AM | 08/01/25 04:00:00 PM | 07/21/25 09:38:00 AM | 08/01/25 05:56:00 AM |
1-00543243 | 6 | OKGET | Disconnect | 3rd Street Disconnect 30 | 69 | 08/07/25 02:23:44 PM | Planned | APPROVED | 09/03/25 08:00:00 AM | 09/03/25 03:00:00 PM | | |
1-00536554 | 5 | LEST | CircuitBreaker | 40th & Bennet 1001 | 115 | 06/25/25 01:16:48 PM | Planned | COMPLETED | 08/06/25 08:00:00 AM | 08/07/25 04:00:00 PM | 08/06/25 09:24:00 AM | 08/07/25 12:43:00 PM |
1-00536554 | 5 | LEST | Disconnect | 40th & Bennet 1001-D1 | 115 | 06/25/25 01:16:48 PM | Planned | COMPLETED | 08/06/25 08:00:00 AM | 08/07/25 04:00:00 PM | 08/06/25 09:24:00 AM | 08/07/25 12:43:00 PM |
1-00536554 | 5 | LEST | Disconnect | 40th & Bennet 1001-D2 | 115 | 06/25/25 01:16:48 PM | Planned | COMPLETED | 08/06/25 08:00:00 AM | 08/07/25 04:00:00 PM | 08/06/25 09:24:00 AM | 08/07/25 12:43:00 PM |
1-00536556 | 5 | LEST | CircuitBreaker | 40th & Bennet 1003 | 115 | 06/25/25 01:22:58 PM | Planned | COMPLETED | 08/11/25 08:00:00 AM | 08/12/25 04:00:00 PM | 08/11/25 08:08:00 AM | 08/12/25 03:27:00 PM |
1-00536556 | 5 | LEST | Disconnect | 40th & Bennet 1003-D1 | 115 | 06/25/25 01:22:58 PM | Planned | COMPLETED | 08/11/25 08:00:00 AM | 08/12/25 04:00:00 PM | 08/11/25 08:08:00 AM | 08/12/25 03:27:00 PM |
1-00536556 | 5 | LEST | Disconnect | 40th & Bennet 1003-D2 | 115 | 06/25/25 01:22:58 PM | Planned | COMPLETED | 08/11/25 08:00:00 AM | 08/12/25 04:00:00 PM | 08/11/25 08:08:00 AM | 08/12/25 03:27:00 PM |
1-00536557 | 5 | LEST | CircuitBreaker | 40th & Bennet 1004 | 115 | 06/25/25 01:26:15 PM | Planned | COMPLETED | 08/13/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/13/25 08:34:00 AM | 08/14/25 09:25:00 PM |
1-00536557 | 5 | LEST | Disconnect | 40th & Bennet 1004-D1 | 115 | 06/25/25 01:26:15 PM | Planned | COMPLETED | 08/13/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/13/25 08:34:00 AM | 08/14/25 09:25:00 PM |
1-00536557 | 5 | LEST | Disconnect | 40th & Bennet 1004-D2 | 115 | 06/25/25 01:26:15 PM | Planned | COMPLETED | 08/13/25 08:00:00 AM | 08/14/25 04:00:00 PM | 08/13/25 08:34:00 AM | 08/14/25 09:25:00 PM |
1-00536551 | 5 | LEST | CircuitBreaker | 40th & Rokeby 1003 | 115 | 06/25/25 01:11:14 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/05/25 04:00:00 PM | 08/04/25 08:05:00 AM | 08/05/25 12:53:00 PM |
1-00536551 | 5 | LEST | Disconnect | 40th & Rokeby 1003-D1 | 0 | 06/25/25 01:11:14 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/05/25 04:00:00 PM | 08/04/25 08:05:00 AM | 08/05/25 12:53:00 PM |
1-00536551 | 5 | LEST | Disconnect | 40th & Rokeby 1003-D2 | 0 | 06/25/25 01:11:14 PM | Planned | COMPLETED | 08/04/25 08:00:00 AM | 08/05/25 04:00:00 PM | 08/04/25 08:05:00 AM | 08/05/25 12:53:00 PM |
1-00516977 | 3 | WRT | Line | 47THWEBB - 64TH 138 KV | 138 | 02/24/25 04:21:34 PM | Planned | PREAPPROVED | 09/08/25 09:00:00 AM | 09/26/25 02:00:00 PM | | |
1-00527649 | 23 | WRT | Line | 4th & Van Buren - North Tyler 115 kV | 115 | 05/12/25 07:43:43 PM | Planned | COMPLETED | 08/20/25 09:00:00 AM | 08/30/25 04:00:00 PM | 08/20/25 02:18:00 PM | 08/29/25 02:18:00 PM |
1-00527649 | 23 | WRT | CircuitBreaker | 4th & Van Buren 115-692 | 115 | 05/12/25 07:43:43 PM | Planned | COMPLETED | 08/20/25 09:00:00 AM | 08/30/25 04:00:00 PM | 08/20/25 02:18:00 PM | 08/29/25 02:18:00 PM |
1-00536495 | 2 | WRT | Disconnect | 4th & Van Buren 115-693 | 0 | 06/25/25 08:46:37 AM | Planned | PREAPPROVED | 10/13/25 08:00:00 AM | 11/07/25 04:00:00 PM | | |
1-00527649 | 23 | WRT | CircuitBreaker | 4th & Van Buren 115-700 | 115 | 05/12/25 07:43:43 PM | Planned | COMPLETED | 08/20/25 09:00:00 AM | 08/30/25 04:00:00 PM | 08/20/25 02:18:00 PM | 08/29/25 02:18:00 PM |
1-00526762 | 2 | WRT | Line | 54th & Meriden - County Line WR 115 kV | 115 | 05/05/25 11:25:27 AM | Planned | PREAPPROVED | 09/08/25 08:00:00 AM | 09/17/25 03:00:00 PM | | |
1-00526762 | 2 | WRT | Disconnect | 54th & Meriden 115-832 | 0 | 05/05/25 11:25:27 AM | Planned | PREAPPROVED | 09/08/25 08:00:00 AM | 09/17/25 03:00:00 PM | | |
1-00542950 | 3 | LEST | Line | 56th & Everett - 56th & Q 115 kV | 115 | 08/06/25 07:22:09 AM | Planned | PREAPPROVED | 10/22/25 12:00:00 PM | 10/30/25 04:00:00 PM | | |
1-00542950 | 3 | LEST | CircuitBreaker | 56th & Everett 1064-L | 115 | 08/06/25 07:22:09 AM | Planned | PREAPPROVED | 10/22/25 12:00:00 PM | 10/30/25 04:00:00 PM | | |
1-00510924 | 6 | LEST | Disconnect | 56th & I-80 1061L | 115 | 01/20/25 02:33:28 PM | Planned | IMPLEMENTED | 07/14/25 08:00:00 AM | 10/20/25 04:00:00 PM | 07/14/25 07:59:00 AM | |
1-00542786 | 4 | LEST | Line | 56th & Q - 57th & Garland 115 kV | 115 | 08/05/25 09:05:26 AM | Planned | PREAPPROVED | 10/13/25 08:00:00 AM | 10/22/25 12:00:00 PM | | |
1-00542786 | 4 | LEST | CircuitBreaker | 56th & Q 1001 | 115 | 08/05/25 09:05:26 AM | Planned | PREAPPROVED | 10/13/25 08:00:00 AM | 10/22/25 12:00:00 PM | | |
1-00542950 | 3 | LEST | CircuitBreaker | 56th & Q 1001 | 115 | 08/06/25 07:22:09 AM | Planned | PREAPPROVED | 10/22/25 12:00:00 PM | 10/30/25 04:00:00 PM | | |
1-00542786 | 4 | LEST | Disconnect | 56th & Q 1001-D1 | 115 | 08/05/25 09:05:26 AM | Planned | PREAPPROVED | 10/13/25 08:00:00 AM | 10/22/25 12:00:00 PM | | |